On Dec 2, 2008 a kickoff meeting for the spex upgrade and the ishell instrument project was given to the IRTF staff in Hilo.
Meeting Documents
iSHELL_presentation_outline.txt
iSHELL_presentation.pdf - General description of icshell by A.Tokunaga.
spex_presentation.pdf - Spex upgrade presentation by J.Rayner (NOT AVAILABLE YET).
click on image for full size picture.
SpeX_Upgrade_proposal_30oct07.pdf - SpeX's upgrade proposal document.
icshell_proposal_short.pdf - The project description portion from the icshell proposal.
denault's comments. (12/3/2008)
koenig's comments. (12/5/2008)
hawarden's comments. (12/5/2008)